Christies Beach Ocean Outfall

Christies Beach Ocean Outfall

OCEL Consultants NZ Limited were engaged by Smithbridge Australia to provide the design of the outfall pipeline and the temporary works for the South Australian Water Board effluent outfall from the water treatment plant at Christies Beach, Adelaide, South Australia. The outfall pipe is a 1,200 mm outside diameter steel pipe with a 12.7 mm wall thickness, internally lined with mortar and with a 120 mm thick concrete weight coat. The length of the outfall is 621 m. The project was completed in November 2009.

christies